Construction at Realm Condominiums is moving forward with exciting progress across both towers. As summer unfolds, our teams are working diligently to bring this vibrant community to life. Here’s a look at the July milestones for Buildings C and D.
BUILDING D HIGHLIGHTS
- Structure: The MPH (Mechanical Penthouse) roof is now complete, marking a major step in the building’s structural progress.
- Windows: Installation has reached the 11th floor, enhancing the building’s exterior appearance.
- Mechanical Riser: Completed up to the 14th floor, ensuring smooth systems integration as construction advances.
- Block Walls: Completed up to the 8th floor, adding to the stability and progress of the internal structure.
- Hallway Drywall Framing: Now underway on the 8th floor.
- Ground Floor Waterproofing: Currently in progress, ensuring durability and protection for years to come.
- Suite Finishes: Work is advancing from the ground floor through to the 3rd floor.
- Landscaping: Taking shape on the 6th floor, adding greenery to the future living spaces.
BUILDING C HIGHLIGHTS
- Structure: The 15th floor is being poured, continuing the steady upward momentum.
- Windows: Installation is in progress up to the 9th floor, adding character to the building’s façade.
- Mechanical Riser: Reaching up to the 9th floor.
- Hallway Drywall Framing: In progress on the 6th floor.
- Suite Finishes: Ongoing on the ground and 2nd floors, shaping interiors into future homes.